77.3%
Overall Completion
Project Details
Machine Number
SPM808
SPM808
Customer
Gabriel-Khandsa
Gabriel-Khandsa
IO Number
1411000080
1411000080
Design Lead
Prabhakaran
Prabhakaran
Designer
Mallikarjun
Mallikarjun
Supplier
GTRP
GTRP
Cost (MINR)
4.5
4.5
Target
September
September
Current Status
Rework/ tooling procurement in process
Rework/ tooling procurement in process
Work Activities: Machine assembly, wiring,testing
Stage Completion
Stage A
100%
Stage B
100%
Stage C
100%
Stage D
100%
Stage E
64%
Stage F
0%
Milestones
Std Release
Std Ordered
Mfg Release
Mfg Ordered
Inspection
Assembly
Internal Trial
Despatch
Commissioning
Manuals
Materials Summary · Manufacturing & Boughtouts
As of 02-11-2026
No BOM uploaded yet - upload the Standard BOM to see the materials summary.
By Type
No BOM cost recorded yet.
Budget vs Actual
Cost (MINR) vs live BOM cost
Needs both a Cost (MINR) budget and a BOM upload to compare.
Process Flow Checklist
Bulk update via Excel: export the current checklist, edit Status/Start Date/End Date/Note, then upload it back here.
Matched by Task Number, so reordering or renaming other columns is safe.
Standard BOM (Bill of Materials)
No Standard BOM uploaded yet for this project.
Timeline & Gantt Chart (Plan vs Actual)
A curated set of milestones, each covering a range of Process Flow Checklist tasks - each one shown as a weekly Plan row and Actual row, filled in for every calendar week its dates span. Nothing here is editable directly; update the checklist instead, or the milestone list itself under Master Data → Gantt Milestones.
| Milestone | Wk41 | Wk42 | Wk43 | Wk44 | Wk45 | Wk46 | Wk47 | Wk48 | Wk49 | Wk50 | Wk51 | Wk52 | Wk53 | Wk1 | Wk2 | Wk3 | Wk4 | Wk5 | Status |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | ||
| 2026 | 2026 | 2026 | 2026 | 2026 | 2026 | 2026 | 2026 | 2026 | 2026 | 2026 | 2026 | 2026 | 2027 | 2027 | 2027 | 2027 | 2027 | ||
| Design review for Mfg/assembly | On track | ||||||||||||||||||
| Design review for routing & accessibility | On track | ||||||||||||||||||
| STD BOM release | On track | ||||||||||||||||||
| Electrical BOM release | On track | ||||||||||||||||||
| STD RFQ, order finalization & PO release | On track | ||||||||||||||||||
| Electrical order release | On track | ||||||||||||||||||
| Manufacturing BOM release | On track | ||||||||||||||||||
| Mfg RFQ, order finalization & PO release | On track | ||||||||||||||||||
| Manufacturing & Procurement | On track | ||||||||||||||||||
| Electrical items Procurement | On track | ||||||||||||||||||
| Standard items Procurement | On track | ||||||||||||||||||
| Assembly & Alignment completion | On track | ||||||||||||||||||
| Electrical wiring & routing completion | On track | ||||||||||||||||||
| Internal Testing | On track | ||||||||||||||||||
| Trial-1 at GTRP | On track | ||||||||||||||||||
| Despatch | On track | ||||||||||||||||||
Row 2 of the header is the project week number since the first shown week.
Plan
Actual (on track)
Actual (delayed)