GRC Spinning machine

Parwanoo · Regular Process · Asset Code: 9050000116
16.7%
Overall Completion
Project Details
Machine Number
SPM817
Customer
Gabriel-Parwano
IO Number
1411000021
Design Lead
Prabhakaran
Designer
Prabhakaran
Supplier
GTRP
Cost (MINR)
4.6
Target
Dec
Current Status
Ordering in progress
Work Activities: Machine ordered to universal
Stage Completion
Stage A 40%
Stage B 60%
Stage C 0%
Stage D 0%
Stage E 0%
Stage F 0%

Milestones
Std Release Std Ordered Mfg Release Mfg Ordered Inspection Assembly Internal Trial Despatch Commissioning Manuals
Materials Summary · Manufacturing & Boughtouts As of 02-11-2026
GRC Spinning machine · Machine No: SPM817· Asset Code: 9050000116
Received = materials whose Material Status is RECEIVED (from the Material Order Status upload). Release is the latest Standard BOM upload; Target is the project's target. Click a category to see its materials.
Budget vs Actual Cost (MINR) vs live BOM cost
Total Budget ₹4.6 MINR
Actual (live BOM cost) 68.7% of budget ₹3.16 MINR
31.3% of budget still available.
Process Flow Checklist
Export to Excel

Task Description Status Planned Start Planned End Actual Start Actual End Remarks
A1 Capex transfer from plant Completed 17-07-2026 20-07-2026 - 18-09-2026 -
A2 IO number/CWIP Asset code generation Completed 17-07-2026 24-07-2026 - 18-09-2026 -
A3 Project kick-off meeting from Design lead Completed 17-07-2026 24-07-2026 - 18-09-2026 -
A4 Design review for cost reduction Completed 17-07-2026 30-07-2025 - 18-09-2026 -
A5 Design review for project lead time reduction Completed 17-07-2026 30-07-2026 - 18-09-2026 -
A6 Design review for routing & planning NotStarted 17-07-2026 30-07-2026 - - -
A7 Design review for alignment mandril JustStarted 17-07-2026 10-08-2026 22-09-2026 - -
A8 Test chart discussion with Design lead NotStarted 17-07-2026 10-08-2026 - - -
A9 Receiving of standard BOM &Circuits Completed 17-07-2026 10-08-2026 - 18-09-2026 -
A10 Receiving of manufacturing parts &pheriperals InProgress 17-07-2026 10-08-2026 - - -
A11 Receiving of fasteners list JustStarted 17-08-2026 10-09-2026 22-09-2026 - -
A12 Receiving of sub assembly drawings ,test chart NotStarted 17-08-2026 10-09-2026 - - -
A13 Receiving of Customer documents(DAP,DAP-MOM,Customer checksheet,process parameters) NotStarted 17-08-2026 10-09-2026 - - -
A14 Electrical Design Review/ Part list preparation NotStarted 17-08-2026 10-09-2026 - - -
A15 Electrical BOM Preparation NotStarted 17-08-2026 10-09-2026 - - -

Task Description Status Planned Start Planned End Actual Start Actual End Remarks
B1 RFQ to suppliers /Vendor selection Completed 01-08-2026 10-10-2026 - 18-09-2026 -
B2 Categorization of parts in to 3 segments ( critical ,medium , normal type) Completed - - - 18-09-2026 -
B3 Cost comparison/optimization /cost reduction data submission to CFT Completed - - - 18-09-2026 -
B4 Electrical items RFQ/ Quotation /Negotiation Completed - - - 21-09-2026 -
B5 Critical parts ordering Completed 01-08-2026 10-10-2026 - 28-09-2026 -
B6 Release of control panel Completed - - - 28-09-2026 -
B7 Medium &Normal category ordering Completed 01-08-2026 31-10-2026 - 21-09-2026 -
B8 Electrical items (field materials) PO release Completed - - - 21-09-2026 -
B9 PO release to suppliers and confirmation /PO approvals Completed - - - 18-09-2026 -
B10 Cash purchase items procurement Pending - - - - -
B11 Panel inspection & validation NotStarted - - - - -
B12 Parts receipt (Critical parts) & Storage in pallets and racks with identification tag NotStarted - - - - -
B13 Parts receipt (M&Nornal parts) & Storage in pallets and racks with identification tag Pending - - - - -
B14 STD parts procurement & material receipt NotStarted - - - - -
B15 Receipt of control panel and field materials NotStarted - - - - -

Task Description Status Planned Start Planned End Actual Start Actual End Remarks
C1 Trails parts requirment list receipt from design lead NotStarted - - - - -
C2 Follwup with Customer plant for trail parts NotStarted - - - - -
C3 STO preparation and communication to customer NotStarted - - - - -
C4 Receipt of trail parts at shop floor NotStarted - - - - -

Task Description Status Planned Start Planned End Actual Start Actual End Remarks
D1 Study all the drawings for assembly NotStarted - - - - -
D2 Full kit assembly preparation based on BOM and Assembly dwgs NotStarted - - - - -
D3 Base frame scrapping & painting ,levelling NotStarted - - - - -
D4 Panel layout design & DAP approval for control panel NotStarted - - - - -
D5 Sub assembly completion NotStarted - - - - -
D6 Preparation of interlock matrix, address mapping IP list documentation NotStarted - - - - -
D7 Full assembly completion & alignment as per agreed document NotStarted - - - - -
D8 Alignment approval from design lead NotStarted - - - - -
D9 HMI Screen Developing NotStarted - - - - -
D10 Doweling for all assemblies NotStarted - - - - -
D11 Pneumatic piping +pheriperals assy NotStarted - - - - -
D12 Study Technical document, components drawings & RFQ NotStarted - - - - -
D13 Manual Operation Sequence NotStarted - - - - -
D14 Auto / Step Mode Operation Sequence NotStarted - - - - -
D15 Preparation of panel /field wiring NotStarted - - - - -

Task Description Status Planned Start Planned End Actual Start Actual End Remarks
E1 Electrical field wiring completion/power-on NotStarted - - - - -
E2 Check Short Circuit Test in the Panel (No Short Circuit) NotStarted - - - - -
E3 Checking Supply voltage between the Neutral to Earth (Less Than 1V) NotStarted - - - - -
E4 Checking Supply voltage between the Phase (R,Y,B - 415V) / (Phase to Neutral - 230V) NotStarted - - - - -
E5 PLC Inputs & Output and Manual Movement Testing NotStarted - - - - -
E6 Safety Device Testing (E-Stop & Door Switch) NotStarted - - - - -
E7 Step/Auto mode testing NotStarted - - - - -
E8 DAP document checking &sign off with CFT NotStarted - - - - -
E9 Safety check sheet completion & sign off with CFT NotStarted - - - - -
E10 Dry run of machine for > 12 hrs for heat ,noise etc NotStarted - - - - -
E11 Internal trails with min 3 hrs dry run
File required to complete
NotStarted - - - - -

Task Description Status Planned Start Planned End Actual Start Actual End Remarks
F1 Customer visit followup & equipment readiness as per agreed DAP NotStarted - - - - -
F2 Customer trails completion for agreed application NotStarted - - - - -
F3 Trail report preparation and signoff with CFT NotStarted - - - - -
F4 Preparartion of MOM and sign off with CFT NotStarted - - - - -
F5 Design error list preparation and submission to design lead NotStarted - - - - -
F6 RFQ for machine packing & transportation NotStarted - - - - -
F7 Machine load details sharing to transporter NotStarted - - - - -
F8 STO PO followup with customer /Invoice preparation NotStarted - - - - -
F9 MOM points closure and communication to customer NotStarted - - - - -
F10 Photos & Videos of equipment NotStarted - - - - -
F11 Manuals (Mechanical +Electrical ) printouts NotStarted - - - - -
F12 Machine packing NotStarted - - - - -
F13 Trials Parts STO closure or scrap clearence NotStarted - - - - -
F14 Insurance confirmation &Machine dispatch NotStarted - - - - -
F15 Communication to customer about machine dispatch NotStarted - - - - -
F16 Commissioning site readiness document preparation and submission to customer NotStarted - - - - -
F17 Machine installation & commissioning for agreed models NotStarted - - - - -
F18 Trails & observation points closure NotStarted - - - - -
F19 Training -Operators/Maintenance/TSG & handover NotStarted - - - - -
F20 MOM points closure and signoff NotStarted - - - - -

Bulk update via Excel: export the current checklist, edit Status/Start Date/End Date/Note, then upload it back here. Matched by Task Number, so reordering or renaming other columns is safe.
Standard BOM (Bill of Materials) BOM Total Cost: 3,160,100.02 · FY 2026-27

Live BOM: 318 material(s) · total cost 3,160,100.02 - re-uploading overwrites a material already here (matched by Part No. + Specification) and adds anything new; it never removes existing materials.

As per file
Plant: -
Machine: GRC SPINNING MACHINE
Asset Code: 9050000116
Assly. No.: -
Assy Des.: -
This project's own values
Plant: Parwanoo
Machine: GRC Spinning machine
Latest upload (file contents)
File: Standard_BOM_Template (002) (1).xlsx
That file had: 318 line(s), total 3,160,100.02
By contact@themars.in on 22-09-2026 17:34
Assembly No.TypeCriticalPart No.Specification DescriptionQtyMakeUnit Price Total PricePO NoPO DateSupplier Ordered QtyReceived QtyPending QtyStatus
SPM817-01-00 BASE ASSEMBLY Manufacturing No SPM817-01A-00 BASE FRAME 1.000 0.00 0.00 4100003381 H.V.ENTERPRISES 1 0 1 PENDING
Manufacturing No SPM817-01-01 COLUMN 1.000 0.00 0.00 4100003381 H.V.ENTERPRISES 1 0 1 PENDING
Manufacturing No SPM817-01-02 ADJ BLK 2.000 1,848.00 3,696.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-01-03 SENSOR MTG HOME 2.000 427.50 855.00 4100003209 01-09-2026 MANGALAA 2 2 0 RECEIVED
Manufacturing No SPM817-01-04 BKT 1.000 1,584.00 1,584.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-01-05 SENSOR MTG PL 1.000 855.00 855.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-01-06 POSITION PIN 1.000 572.00 572.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-01-08 TOP PLATE 1.000 26,048.00 26,048.00 4100003210 01-09-2026 EMM KAY 2 0 1 PENDING
Manufacturing No SPM817-01-09 KEY 1.000 585.00 585.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-01-10 KEY 1.000 572.00 572.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-01-12 BUTT BLOCK 2.000 882.00 1,764.00 4100003208 01-09-2026 PONNI 2 0 2 PENDING
Manufacturing No SPM817-01-13 BACK TOP SHEET 1.000 845.50 845.50 4100003209 01-09-2026 MANGALAA 1 1 0 RECEIVED
Manufacturing No SPM817-01-14 SENSOR MTG BKT NEW 1.000 0.00 0.00 0 0 1 NOT ORDERED
Manufacturing No SPM817-01-15 SIDE SHEET 1.000 380.00 380.00 4100003209 01-09-2026 MANGALAA 1 1 0 RECEIVED
Manufacturing No SPM817-01-16 KEY 8.000 396.00 3,168.00 4100003210 01-09-2026 EMM KAY 8 0 8 PENDING
Manufacturing No SPM817-01-17 TOOL RACK 1.000 0.00 0.00 0 0 1 NOT ORDERED
Manufacturing No SPM817-01-18 LOAD CELL MNT PLATE 1.000 2,816.00 2,816.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-01-19 GUIDE PINS 2.000 484.00 968.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-01-20 LOAD CELL TOP PLATE 1.000 2,992.00 2,992.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-01-21 TOP WASHER 2.000 225.00 450.00 4100003208 01-09-2026 PONNI 2 0 2 PENDING
Manufacturing No SPM817-01-23 STUD 1.000 0.00 0.00 0 0 1 NOT ORDERED
Manufacturing No SPM817-01-24 BACK SHEET 1 2.000 3,021.00 6,042.00 4100003209 01-09-2026 MANGALAA 2 2 0 RECEIVED
Manufacturing No SPM817-01-25 REJECTION BIN STAND 2.000 1,662.50 3,325.00 4100003209 01-09-2026 MANGALAA 2 2 0 RECEIVED
SPM813-02-00 DRIVE ASSEMBLY Manufacturing No SPM817-02-01 SPACER 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
Manufacturing No SPM817-02-02 MOTOR MTG PLATE 1.000 0.00 0.00 4100003370 PONNI ENGINEERING 1 0 1 PENDING
Manufacturing No SPM817-02-03 CLAMPING WASHER 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
Manufacturing No SPM817-02-04 TENSIONING BLOCK 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
Manufacturing No SPM817-02-05 COVER 1.000 0.00 0.00 4100003370 PONNI ENGINEERING 1 0 1 PENDING
Manufacturing No SPM817-02-06 MOTOR MOUNTING BKT 3 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
SPM817-03-00 DRIVEN ASSEMBLY Manufacturing No SPM817-03-02 KEY 1.000 572.00 572.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-03-03 COVER PLATE 1.000 4,752.00 4,752.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-03-04 SLIDING PLATE-NEW 1.000 15,615.00 15,615.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-03-05 BUSHING 1.000 3,432.00 3,432.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-03-06 SHAFT NEW 1.000 6,952.00 6,952.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-03-07 FLANGE COVER 2.000 2,552.00 5,104.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-03-08 SPACER-1 1.000 880.00 880.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-03-10 COVER BOX 1.000 8,536.00 8,536.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-03-11 BOTTOM HOUSING 1.000 16,110.00 16,110.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-03-12 SPACER-2 1.000 1,056.00 1,056.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-03-13 KEY 1.000 315.00 315.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-03-14 PLATE 1.000 9,450.00 9,450.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-03-15 PLATE 1.000 9,450.00 9,450.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-03-16 SPACER-3 1.000 396.00 396.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-03-17 KEY 3.000 315.00 945.00 4100003208 01-09-2026 PONNI 3 0 3 PENDING
Manufacturing No SPM817-03-19 CLAMPING WASHER 1.000 572.00 572.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-03-20 DOG PIN 1.000 308.00 308.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
SPM817-04-00 BALL SPLINE ARRANGEMENT Manufacturing No SPM817-04A-00 BALL SPLINE WITH NUT 1.000 0.00 0.00 0 0 1 NOT ORDERED
Manufacturing No SPM817-04-01 BOTTOM SPLINE SUPPORT 1.000 9,450.00 9,450.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-04-02 TOP SPLINE SUPPORT 1.000 5,310.00 5,310.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-04-03 BEARING HOUSING 2.000 10,350.00 20,700.00 4100003208 01-09-2026 PONNI 2 0 2 PENDING
Manufacturing No SPM817-04-04 NUT HOUSING 3.000 5,192.00 15,576.00 4100003210 01-09-2026 EMM KAY 3 0 3 PENDING
Manufacturing No SPM817-04-05 SPACER-1 3.000 1,260.00 3,780.00 4100003208 01-09-2026 PONNI 3 0 3 PENDING
Manufacturing No SPM817-04-06 SPACER-2 3.000 1,672.00 5,016.00 4100003210 01-09-2026 EMM KAY 3 0 3 PENDING
Manufacturing No SPM817-04-07 SPACER-3 3.000 990.00 2,970.00 4100003208 01-09-2026 PONNI 3 0 3 PENDING
Manufacturing No SPM817-04-08 CLAMPING PLATE 3.000 1,485.00 4,455.00 4100003208 01-09-2026 PONNI 3 0 3 PENDING
Manufacturing No SPM817-04-09 FIXED BRACKET 1.000 0.00 0.00 0 0 1 NOT ORDERED
Manufacturing No SPM817-04-10 IDLER PULLEY PIN NEW 2.000 1,215.00 2,430.00 4100003208 01-09-2026 PONNI 2 0 2 PENDING
Manufacturing No SPM817-04-11 IDLER PULLEY 2.000 1,980.00 3,960.00 4100003208 01-09-2026 PONNI 2 0 2 PENDING
Manufacturing No SPM817-04-12 WASHER 2.000 308.00 616.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-04-13 SPACER-4 2.000 630.00 1,260.00 4100003208 01-09-2026 PONNI 2 0 2 PENDING
Manufacturing No SPM817-04-14 SPACER-5 2.000 540.00 1,080.00 4100003208 01-09-2026 PONNI 2 0 2 PENDING
Manufacturing No SPM817-04-15 FITMENT SPACER 1.000 2,552.00 2,552.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-04-16 MOVING BRACKET BOTTOM 1.000 15,400.00 15,400.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-04-17 FITMENT SPACER TOP 2.000 880.00 1,760.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-04-18 FITMENT SPACER MIDDLE 2.000 1,575.00 3,150.00 4100003208 01-09-2026 PONNI 2 0 2 PENDING
Manufacturing No SPM817-04-19 BOTTOM SPACER 1.000 2,464.00 2,464.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-04-20 SPACER 2.000 352.00 704.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-04-21 SPACER 2.000 1,170.00 2,340.00 4100003208 01-09-2026 PONNI 2 0 2 PENDING
Manufacturing No SPM817-04-23 KEY 1.000 660.00 660.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-04-24 IDLER PLATE 2.000 3,432.00 6,864.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-04-25 WASHER 2 2.000 264.00 528.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-04-27 MOVING PLATE 1.000 19,184.00 19,184.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-04-28 ACTUATOR MTG PLATE 1.000 2,655.00 2,655.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-04-29 COUPLER 1.000 1,512.00 1,512.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
SPM817-05-00 CLAMPING ARRANGEMENT Manufacturing No SPM817-05-01 HARDENED BUSH 1.000 3,285.00 3,285.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-05-02 SPINDLE HOUSING 1.000 18,810.00 18,810.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-05-03 FLANGE COVER 2.000 1,936.00 3,872.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-05-04 SHAFT 1.000 6,210.00 6,210.00 4100003208 01-09-2026 PONNI 2 0 1 PENDING
Manufacturing No SPM817-05-05 JOB HOLDER NEW 1.000 0.00 0.00 0 0 1 NOT ORDERED
Manufacturing No SPM817-05-06 SPACER-1 1.000 882.00 882.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-05-07 SPACER-2 1.000 704.00 704.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-05-08 SPACER-3 2.000 792.00 1,584.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-05-09 COVER 1.000 741.00 741.00 4100003209 01-09-2026 MANGALAA 1 1 0 RECEIVED
Manufacturing No SPM817-05-10 SPACER-4 1.000 308.00 308.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-05-11 SPACER 1.000 880.00 880.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-05-12 PLATE 1.000 1,232.00 1,232.00 4100003210 01-09-2026 EMM KAY 2 0 1 PENDING
Manufacturing No SPM817-05-13 CLAMPING SPACER 1.000 308.00 308.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-05-14 DOG 2.000 0.00 0.00 0 0 2 NOT ORDERED
Manufacturing No SPM817-05-15 BALANCING BLOCK S 1.000 0.00 0.00 0 0 1 NOT ORDERED
Manufacturing No SPM817-05-16 KEY 2.000 308.00 616.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-05-17 KEY-2 1.000 308.00 308.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
SPM817-06-00 TOP PRESSING ARRANGEMENT Manufacturing No SPM817-06-01 MOUNTING BRACKET 1.000 23,496.00 23,496.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-06-02 SLIDING PLATE 1.000 5,580.00 5,580.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-06-03 ROLLER MTG BLOCK NEW 1.000 5,236.00 5,236.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-06-04 SPACER-1 1.000 1,848.00 1,848.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-06-05 POSITION PIN 1.000 572.00 572.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-06-06 ELECTRIC CYL MTG PLATE 1.000 2,790.00 2,790.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-06-07 CLAMP PLATE NEW 2.000 1,056.00 2,112.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-06-08 FLANGE 1.000 1,408.00 1,408.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-06-09 GUIDE BUSH 2.000 1,485.00 2,970.00 4100003208 01-09-2026 PONNI 2 0 2 PENDING
Manufacturing No SPM817-06-10 GUIDE ROD 2.000 572.00 1,144.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-06-11 BOTTOM PLATE 1.000 2,332.00 2,332.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-06-12 WASHER 2.000 220.00 440.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-06-14 HARD STOPPER 1 1.000 528.00 528.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-06-15 SPACER 1.000 2,112.00 2,112.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-06-16 SPACER - NEW 1.000 405.00 405.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-06-17 SLEEVE 1.000 1,260.00 1,260.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-06-18 WASHER 1.000 0.00 0.00 0 0 1 NOT ORDERED
Manufacturing No SPM817-06-19 LOAD CELL MTG PLATE 1.000 2,772.00 2,772.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-06-20 HARD STOPPER 2 1.000 572.00 572.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-06-21 THIN NUT 2.000 0.00 0.00 0 0 2 NOT ORDERED
Manufacturing No SPM817-06-22 ROLLER SPACER 1.000 0.00 0.00 0 0 1 NOT ORDERED
Manufacturing No SPM817-06-23 HARD STOPPER TOP 1.000 660.00 660.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-06-24 COUPLER 1.000 1,364.00 1,364.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
SPM817-07-00 BENDING ROLLER ASSY Manufacturing No SPM817-07-01 MTG BKT 1.000 12,760.00 12,760.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-07-02 HOUSING 1.000 25,020.00 25,020.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-07-03 HOUSING COVER 1.000 6,512.00 6,512.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-07-04 NUT MTG BLOCK 1.000 6,732.00 6,732.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-07-05 GEAR BOX COVER 1.000 3,960.00 3,960.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-07-06 PIN-NEW 1.000 1,672.00 1,672.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-07-07 WASHER 1.000 264.00 264.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-07-08 SPACER 2.000 484.00 968.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-07-09 OIL SEAL COVER 1.000 1,936.00 1,936.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-07-10 WASHER - DRIVER 1.000 264.00 264.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-07-11 CONNECTING PLATE 1.000 2,596.00 2,596.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-07-12 ROLLER HOLDER BLOCK-NEW 1.000 10,170.00 10,170.00 4100003208 01-09-2026 PONNI 1 0 1 PENDING
Manufacturing No SPM817-07-13 FITMENT SPACER 2.000 484.00 968.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-07-14 SPACER-NEW 2.000 572.00 1,144.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-07-15 STOPPER 1.000 572.00 572.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-07-16 DOG MTG BLOCK 1.000 1,408.00 1,408.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-07-17 GEAR BOX HOUSING 1.000 14,872.00 14,872.00 4100003210 01-09-2026 EMM KAY 1 0 1 PENDING
Manufacturing No SPM817-07-18 DRIVE GEAR 1.000 13,500.00 13,500.00 4100003246 04-09-2026 KRISHNA 3 1 0 PENDING
Manufacturing No SPM817-07-19 DRIVEN GEAR 1.000 15,000.00 15,000.00 4100003246 04-09-2026 KRISHNA 3 1 0 PENDING
Manufacturing No SPM817-07-20 COVER 1.000 741.00 741.00 4100003209 01-09-2026 MANGALAA 1 1 0 RECEIVED
Manufacturing No SPM817-07-21 KEY 2.000 495.00 990.00 4100003208 01-09-2026 PONNI 2 0 2 PENDING
Manufacturing No SPM817-07-22 FITMENT SPACER 2.000 2,332.00 4,664.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-07-23 DOG 2.000 572.00 1,144.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-07-24 KEY 2.000 308.00 616.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
Manufacturing No SPM817-07-25 KEY 3 2.000 264.00 528.00 4100003210 01-09-2026 EMM KAY 2 0 2 PENDING
SPM817-08-00 LH SUPPORT ROLLER ASSEMBLY Manufacturing No SPM817-08-01 ROLLER HOLDER BLOCK-2 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
Manufacturing No SPM817-08-02 ROLLER NEW 4.000 0.00 0.00 4100003370 PONNI ENGINEERING 4 0 4 PENDING
Manufacturing No SPM817-08-03 ROLLER PIN-2 4.000 0.00 0.00 4100003375 EMM KAY TOOLS 4 0 4 PENDING
Manufacturing No SPM817-08-04 SPACER1 4.000 0.00 0.00 4100003375 EMM KAY TOOLS 4 0 4 PENDING
Manufacturing No SPM817-08-05 NYLON COVER 4.000 0.00 0.00 4100003375 EMM KAY TOOLS 4 0 4 PENDING
Manufacturing No SPM817-08-06 SPACER-2 4.000 0.00 0.00 4100003375 EMM KAY TOOLS 4 0 4 PENDING
Manufacturing No SPM817-08-07 MNT BKT 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
Manufacturing No SPM817-08-08 BUSH HOUSING 1.000 0.00 0.00 4100003370 PONNI ENGINEERING 1 0 1 PENDING
Manufacturing No SPM817-08-09 SUPPORT ROLLER MNT BASE 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
Manufacturing No SPM817-08-10 FLANGE 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
Manufacturing No SPM817-08-11 COUPLER 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
Manufacturing No SPM817-08-12 FITMENT SPACER 2.000 0.00 0.00 4100003370 PONNI ENGINEERING 1 0 2 PENDING
Manufacturing No SPM817-08-13 GUIDE ROD 4.000 0.00 0.00 4100003370 PONNI ENGINEERING 4 0 4 PENDING
Manufacturing No SPM817-08-14 FITMENT SPACER 2 1.000 0.00 0.00 4100003370 PONNI ENGINEERING 1 0 1 PENDING
SPM817-09-00 RH SUPPORT ROLLER ASSEMBLY Manufacturing No SPM817-09-01 ROLLER HOLDER BLOCK-2 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
Manufacturing No SPM817-09-02 FITMENT SPACER 2.000 0.00 0.00 4100003370 PONNI ENGINEERING 1 0 2 PENDING
Manufacturing No SPM817-09-03 BUSH HOUSING 1.000 0.00 0.00 4100003370 PONNI ENGINEERING 1 0 1 PENDING
Manufacturing No SPM817-09-04 SUPPORT ROLLER MNT BASE 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
Manufacturing No SPM817-09-05 MNT BKT 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
Manufacturing No SPM817-09-06 COUPLER 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
Manufacturing No SPM817-09-07 FLANGE 1.000 0.00 0.00 4100003375 EMM KAY TOOLS 1 0 1 PENDING
Manufacturing No SPM817-09-08 FITMENT SPACER -2 1.000 0.00 0.00 4100003370 PONNI ENGINEERING 1 0 1 PENDING
SPM817-01 BASE ASSY Standard No VBG1200xM20x100 DIA 165 ANTI VIBRATION MOUNTS 4.000 VIBRO 970.00 3,880.00 4100003281 08-09-2026 VIBRO 4 4 0 RECEIVED
Standard No BGHW6006ZZ-40-40 BEARING HOUSING 3.000 MISUMI 7,180.70 21,542.10 4100003277 08-09-2026 SAI RAM 3 0 3 PENDING
Standard No KM6 LOCKNUT 3.000 SKF 60.00 180.00 4100003278 08-09-2026 International 0 0 3 NOT ORDERED
Standard No MB 7 LOCK WASHER 3.000 SKF 20.00 60.00 4100003278 08-09-2026 International 0 0 3 NOT ORDERED
SPM817-02 DRIVE ASSY Standard No HTBN 1246 S14M-600 TIMING BELT 1.000 MISUMI 13,532.75 13,532.75 4100003277 08-09-2026 SAI RAM 2 0 1 PENDING
Standard No HTPTNF28-S14M600-A-C30 TIMING PULLEY 1.000 MISUMI 0.00 0.00 4100003277 08-09-2026 SAI RAM 1 1 0 RECEIVED
Standard No VRL-205C-3-K5-65MB55 Gear Box 1.000 NANDI 115,291.00 115,291.00 4100003053 08-08-2026 NANDI CONTROL 1 0 1 PENDING
SPM817-03 DRIVEN ARRANGEMENT Standard No HGH35HA2R700Z0H+E2 (E1=20,E2=40) LM RAIL & BLOCK 2.000 HIWIN 9,998.00 19,996.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No HTPTNF28-S14M600-A-C30 TIMING PULLEY 1.000 MISUMI 0.00 0.00 4100003277 08-09-2026 SAI RAM 1 1 0 RECEIVED
Standard No DIN 3760 A A - 58 x 72 x 8 - NBR OIL SEAL 4.000 STD 340.00 1,360.00 4100003278 08-09-2026 International 4 0 4 PENDING
Standard No STN 024730 SKF (A) - SKF 51210 BEARING 1.000 SKF 3,016.00 3,016.00 4100003278 08-09-2026 International 1 0 1 PENDING
Standard No STN 024645 ZKL (A) - ZKL 7208B BEARING 1.000 ZKL 2,900.00 2,900.00 4100003278 08-09-2026 International 1 0 1 PENDING
Standard No GPA6A Greasing Nipple M6 4.000 MISUMI 30.40 121.60 4100003277 08-09-2026 SAI RAM 4 0 4 PENDING
Standard No STN 02 4630 - 6010 50 x 80 x 16 BEARING 1.000 SKF 640.00 640.00 4100003278 08-09-2026 International 1 0 1 PENDING
SPM817-04 BALL SPLINE ASSY Standard No HTPTNF28-S14M600-A-C30 TIMING PULLEY 3.000 MISUMI 0.00 0.00 4100003277 08-09-2026 SAI RAM 1 1 2 PENDING
Standard No SKF 2Z- with two shields SKF 2Z6006-2Z BEARING 4.000 SKF 298.00 1,192.00 4100003278 08-09-2026 International 4 0 4 PENDING
Standard No SKF 2Z6207-2Z BEARING 2.000 SKF 427.00 854.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No SKF 2Z6017-2Z BEARING 6.000 SKF 4,979.00 29,874.00 4100003278 08-09-2026 International 6 0 6 PENDING
Standard No STN 02 3630 - KM 17(3) LOCK NUT 3.000 STD 280.00 840.00 4100003278 08-09-2026 International 3 0 3 PENDING
Standard No STN 023640 - MB17 LOCK WASHER 3.000 STD 45.00 135.00 4100003278 08-09-2026 International 3 0 3 PENDING
Standard No IS 3075-2 55x2 CIRCLIP B Type 2.000 STD 16.00 32.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No ANSI B 27.7M 3BMI-28 CIRCLIP A Type 2.000 STD 5.00 10.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No HTBN 1246 S14M-600 TIMING BELT 1.000 MISUMI 13,532.75 13,532.75 4100003277 08-09-2026 SAI RAM 2 0 1 PENDING
Standard No 574105 ESBF-BS-80-300-5P Electric cylinder 1.000 FESTO 70,341.33 70,341.33 4100003010 04-08-2026 FESTO 1 1 0 RECEIVED
Standard No 1589614 EAMM-U-110-D80-80G-120 Parallel Kit 1.000 FESTO 23,884.92 23,884.92 4100003010 04-08-2026 FESTO 3 3 0 RECEIVED
Standard No 2297691 EMGA-80-P-G5-EAS-80 Gear Box 1.000 FESTO 17,766.82 17,766.82 4100003010 04-08-2026 FESTO 1 1 0 RECEIVED
Standard No 8172026 EMMT-AS-80-H-HS-RMB Servo Motor 1.000 FESTO 41,036.18 41,036.18 4100003010 04-08-2026 FESTO 1 1 0 RECEIVED
Standard No 5251382 NEBM-M23G15-EH-5-Q9N-R3LEG14 Cable 1.000 FESTO 6,325.97 6,325.97 4100003010 04-08-2026 FESTO 4 4 0 RECEIVED
Standard No 8143167 CMMT-AS-C5-11A-P3-MP-S1 Servo Drive 1.000 FESTO 51,205.40 51,205.40 4100003010 04-08-2026 FESTO 4 4 0 RECEIVED
Standard No 3LBF50UU+1850L Ball Spline 1.000 THK 0.00 0.00 4100002970 29-07-2026 Durga bearing 2 0 1 PENDING
SPM817-05 TOP CLAMPING ASSY Standard No HTBN1400S14M-600 TIMING BELT 1.000 MISUMI 15,169.60 15,169.60 4100003277 08-09-2026 SAI RAM 1 0 1 PENDING
Standard No HTPTNF28-S14M600-A-C30 TIMING PULLEY 1.000 MISUMI 0.00 0.00 4100003277 08-09-2026 SAI RAM 1 1 0 RECEIVED
Standard No DIN 3760 - A - 58 x 72 x 8 - NBR OIL SEAL 2.000 STD 240.00 480.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No DIN 625 SKF - SKF 6010-2Z BEARING 1.000 SKF 640.00 640.00 4100003278 08-09-2026 International 1 0 1 PENDING
Standard No SKF 208 BEARING 1.000 SKF 580.00 580.00 4100003278 08-09-2026 International 2 0 1 PENDING
Standard No DIN 711 - 512 10 - 50 x 78 x 22 BEARING 1.000 SKF 3,016.00 3,016.00 4100003278 08-09-2026 International 1 0 1 PENDING
Standard No SKF 208 DEEP GROVE BALL BEARING 1.000 SKF 580.00 580.00 4100003278 08-09-2026 International 2 0 1 PENDING
SPM817-06 TOP PRESSING ASSY Standard No SWU21-25 COIL SPRING 2.000 MISUMI 133.23 266.46 4100003277 08-09-2026 SAI RAM 2 0 2 PENDING
Standard No HGH35HA1R250Z0H+E2 (E1=E2=30) LM RAIL & BLOCK 2.000 HIWIN 4,310.00 8,620.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No RNA4905 NEEDLE BEARING 2.000 SKF 745.00 1,490.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No 51206 THRUST BEARING 2.000 SKF 1,413.00 2,826.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No 574091 ESBF-BS-80-50-5P Electric Cylinder 1.000 FESTO 72,642.52 72,642.52 4100003010 04-08-2026 FESTO 2 2 0 RECEIVED
Standard No 1589614 EAMM-U-110-D80-80G-120 Parallel Kit 1.000 FESTO 23,884.92 23,884.92 4100003010 04-08-2026 FESTO 3 3 0 RECEIVED
Standard No 2297690 EMGA-80-P-G3-EAS-80 Gear Box 1.000 FESTO 17,766.82 17,766.82 4100003010 04-08-2026 FESTO 2 2 0 RECEIVED
Standard No 5255448 EMMT-AS-80-L-HS-RMB Servo Motor 1.000 FESTO 38,598.38 38,598.38 4100003010 04-08-2026 FESTO 1 1 0 RECEIVED
Standard No 5251382 NEBM-M23G15-EH-5-Q9N-R3LEG14 Cable 1.000 FESTO 6,325.97 6,325.97 4100003010 04-08-2026 FESTO 4 4 0 RECEIVED
Standard No 8143167 CMMT-AS-C5-11A-P3-MP-S1 Servo Drive 1.000 FESTO 51,205.40 51,205.40 4100003010 04-08-2026 FESTO 4 4 0 RECEIVED
Standard No 175707 SMB-8-FENG-80-100 Mounting bracket 1.000 FESTO 202.35 202.35 4100003010 04-08-2026 FESTO 0 0 1 NOT ORDERED
Standard No 574334 SMT-8M-A-PS-24V-E-0.3-M8D Reed Switch 1.000 FESTO 742.42 742.42 4100003010 04-08-2026 FESTO 0 0 1 NOT ORDERED
SPM817-07 BENDING ROLLER ASSY LH Standard No HGH20CA2R220Z0H ( E1=E2=20) LM RAIL & BLOCK 2.000 HIWIN 2,390.00 4,780.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No LS 2542 AXIAL BEARING SPACER 2.000 SKF 220.00 440.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No AS2542 AXIAL BEARING SPACER 2.000 SKF 80.00 160.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No AXK 2542 THRUST BEARING 2.000 SKF 120.00 240.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No RNA 6904 NEEDLE BEARING 1.000 SKF 790.00 790.00 4100003278 08-09-2026 International 1 0 1 PENDING
Standard No 28.5X56X2 (LX=2.5)(Lo=3.6) SCHNORR DISC SPRING 2.000 SCHNORR 0.00 0.00 0 0 2 NOT ORDERED
Standard No BS 290 SKF - SKF 7205 BE BEARING 2.000 SKF 1,350.00 2,700.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No ISO 6194_1 - 32x47x8-Type 5 OIL SEAL 2.000 STD 180.00 360.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No DIN 981 - KM 5 LOCK NUT 2.000 MISUMI 55.00 110.00 4100003278 08-09-2026 International 2 0 2 PENDING
Standard No MB 5 LOCK WASHER 2.000 MISUMI 20.00 40.00 4100003278 08-09-2026 International 0 0 2 NOT ORDERED
Standard No 8061401 PLE080-003-SSSA3AE-E19_35_70_90_B5_M5 Gear Box 1.000 FESTO 22,239.31 22,239.31 4100003010 04-08-2026 FESTO 0 0 1 NOT ORDERED
Standard No 5255446 EMMT-AS-80-L-HS-RM Servo Motor 1.000 FESTO 32,097.61 32,097.61 4100003010 04-08-2026 FESTO 3 3 0 RECEIVED
Standard No 5251382 NEBM-M23G15-EH-5-Q9N-R3LEG14 Cable 1.000 FESTO 6,325.97 6,325.97 4100003010 04-08-2026 FESTO 4 4 0 RECEIVED
Standard No 8143167 CMMT-AS-C5-11A-P3-MP-S1 Servo Drive 1.000 FESTO 51,205.40 51,205.40 4100003010 04-08-2026 FESTO 4 4 0 RECEIVED
Standard No R32-5T4-FSI-L1-L1-0.018, Length -275mm BALL SCREW WITH NUT 1.000 HIWIN 0.00 0.00 0 0 1 NOT ORDERED
SPM817-08 LH SUPPORT ROLLER ASSY Standard No 1376657 DSBC -40-40-PPVA-N3 Standard-BASED CYLINDER 1.000 FESTO 2,677.74 2,677.74 4100003203 29-08-2026 FESTO 1 0 1 PENDING
Standard No 574231 VUVG-L14-P53C-T-G18-1R8L SOLENOID VALVE 1.000 FESTO 3,457.02 3,457.02 4100003203 29-08-2026 FESTO 3 0 1 PENDING
Standard No 151689 KMEB-1-24-5-LED CABLE 2.000 FESTO 838.99 1,677.98 4100003203 29-08-2026 FESTO 2 0 2 PENDING
Standard No 193970 GR-QS-8 One-way flow control valve 2.000 FESTO 839.47 1,678.94 4100003203 29-08-2026 FESTO 2 0 2 PENDING
Standard No 161419 UC-1/8 SILENCER 3.000 FESTO 170.20 510.60 4100003203 29-08-2026 FESTO 9 0 3 PENDING
Standard No 132999 QS G1/8-10-I PUSH IN FITTING 3.000 FESTO 120.92 362.76 4100003203 29-08-2026 FESTO 9 0 3 PENDING
Standard No 186107 QS G1/8-6-I PUSH IN FITTING 3.000 FESTO 95.49 286.47 4100003203 29-08-2026 FESTO 9 0 3 PENDING
Standard No LM25-UU Linear Bush 4.000 Misumi 103.08 412.32 4100003277 08-09-2026 SAI RAM 8 0 4 PENDING
Standard No DIN 472 40 x 1.7 Internal circlip 4.000 STD 227.72 910.88 4100003278 08-09-2026 International 4 0 4 PENDING
Standard No 153047 QSL-1/4-6 Push in Fittinhg 2.000 FESTO 103.08 206.16 4100003203 29-08-2026 FESTO 2 0 2 PENDING
Standard No AS2035 THRUST WASHER 8.000 SKF 227.72 1,821.76 4100003278 08-09-2026 International 17 1 7 PENDING
Standard No NKI-20 THRUST NEEDLE ROLLER & CASE ASSY 2.000 SKF 1,050.00 2,100.00 4100003278 08-09-2026 International 5 1 1 PENDING
Standard No AXK2035 INNER RING 4.000 SKF 90.00 360.00 4100003278 08-09-2026 International 8 0 4 PENDING
SPM817-09- ROLLER SUPPORT ASSY RH & SPM817-9A Standard No LM25-UU Linear Bush 4.000 Misumi 1,070.33 4,281.32 4100003277 08-09-2026 SAI RAM 8 0 4 PENDING
Standard No DIN 472 40 x 1.7 Internal circlip 4.000 STD 0.00 0.00 4 0 4 PENDING
Standard No AS2035 THRUST WASHER 8.000 SKF 48.00 384.00 4100003278 08-09-2026 International 17 1 7 PENDING
Standard No NKI-20 THRUST NEEDLE ROLLER BEARING 2.000 SKF 1,050.00 2,100.00 4100003278 08-09-2026 International 5 1 1 PENDING
Standard No AXK2035 INNER RING 4.000 SKF 90.00 360.00 4100003278 08-09-2026 International 8 0 4 PENDING
Standard No 574091 ESBF-BS-80-50-5P Electric Cylinder 1.000 FESTO 72,642.52 72,642.52 4100003010 04-08-2026 FESTO 2 2 0 RECEIVED
Standard No 1589614 EAMM-U-110-D80-80G-120 Parallel Kit 1.000 FESTO 23,884.92 23,884.92 4100003010 04-08-2026 FESTO 3 3 0 RECEIVED
Standard No 2297690 EMGA-80-P-G3-EAS-80 Gear Box 1.000 FESTO 17,766.82 17,766.82 4100003010 04-08-2026 FESTO 2 2 0 RECEIVED
Standard No 5255446 EMMT-AS-80-L-HS-RM Servo Motor 1.000 FESTO 32,097.61 32,097.61 4100003010 04-08-2026 FESTO 3 3 0 RECEIVED
Standard No 5251382 NEBM-M23G15-EH-5-Q9N-R3LEG14 Cable 1.000 FESTO 6,325.97 6,325.97 4100003010 04-08-2026 FESTO 4 4 0 RECEIVED
Standard No 8143167 CMMT-AS-C5-11A-P3-MP-S1 Servo Drive 1.000 FESTO 51,205.40 51,205.40 4100003010 04-08-2026 FESTO 4 4 0 RECEIVED
Standard No 175707 SMB-8-FENG-80-100 Mounting bracket 1.000 FESTO 202.35 202.35 4100003010 04-08-2026 FESTO 0 0 1 NOT ORDERED
Standard No 574334 SMT-8M-A-PS-24V-E-0.3-M8D Reed Switch 1.000 FESTO 742.42 742.42 4100003010 04-08-2026 FESTO 0 0 1 NOT ORDERED
SPM817-10 GUARDING ASSY Standard No IN-CS 3210915A E07374514 Service Unit 1/2" FRL 1.000 FESTO 22,868.74 22,868.74 4100003203 29-08-2026 FESTO 0 0 1 NOT ORDERED
Standard No 153137 QST-12-10 T CONNECTOR 10.000 FESTO 227.72 2,277.20 4100003203 29-08-2026 FESTO 10 0 10 PENDING
Standard No 153151 QSY-10 Y CONNECTOR 10.000 FESTO 222.74 2,227.40 4100003203 29-08-2026 FESTO 10 0 10 PENDING
Standard No 153038 QS-8-6 Push in connector 10.000 FESTO 112.73 1,127.30 4100003203 29-08-2026 FESTO 10 0 10 PENDING
Standard No 153039 QS-10-8 Push in connector 10.000 FESTO 142.14 1,421.40 4100003203 29-08-2026 FESTO 10 0 10 PENDING
Standard No 153040 QS-12-10 Push in connector 10.000 FESTO 149.36 1,493.60 4100003203 29-08-2026 FESTO 10 0 10 PENDING
Standard No 153136 QST-10-8 T CONNECTOR 10.000 FESTO 164.85 1,648.50 4100003203 29-08-2026 FESTO 10 0 10 PENDING
Standard No 153135 QST-8-6 T CONNECTOR 10.000 FESTO 142.84 1,428.40 4100003203 29-08-2026 FESTO 10 0 10 PENDING
Standard No 574231 VUVG-L14-P53C-T-G18-1R8L SOLENOID VALVE 2.000 FESTO 3,457.02 6,914.04 4100003203 29-08-2026 FESTO 3 0 2 PENDING
Standard No 161419 UC-1/8 SILENCER 6.000 FESTO 170.20 1,021.20 4100003203 29-08-2026 FESTO 9 0 6 PENDING
Standard No 132999 QS G1/8-10-I PUSH IN FITTING 6.000 FESTO 120.92 725.52 4100003203 29-08-2026 FESTO 9 0 6 PENDING
Standard No 186107 QS G1/8-6-I PUSH IN FITTING 6.000 FESTO 95.49 572.94 4100003203 29-08-2026 FESTO 9 0 6 PENDING
Standard No 19253 DSNU-25-300-PPV-A CYLINDER 2.000 FESTO 2,677.62 5,355.24 4100003203 29-08-2026 FESTO 2 0 2 PENDING
Standard No 193144 GRLA-1-8-QS-6 PUSH IN FITTINGS 5.000 FESTO 507.88 2,539.40 4100003203 29-08-2026 FESTO 0 0 5 NOT ORDERED
Standard No 175096 SMBR-8-25 DNSU SENSOR MOUNTING BKT 4.000 FESTO 162.84 651.36 4100003203 29-08-2026 FESTO 4 0 4 PENDING
Standard No 574334 SMT-8M-A-PS-24V-E-0,3-M8D SENSOR 4.000 FESTO 1,029.70 4,118.80 4100003203 29-08-2026 FESTO 6 2 2 PENDING
Standard No 8078240 NEBA-M12G5-U-5-N-LE4 SENSOR CABLE 4.000 FESTO 791.18 3,164.72 4100003203 29-08-2026 FESTO 4 0 4 PENDING
Standard No 159670 PUN-12X2-BL PLASTIC TUBING 10 m 10.000 FESTO 109.82 1,098.20 4100003203 29-08-2026 FESTO 50 0 10 PENDING
Standard No 159668 PUN-10X1.25-BL PLASTIC TUBING 20 m 20.000 FESTO 80.06 1,601.20 4100003203 29-08-2026 FESTO 0 0 20 NOT ORDERED
Standard No 159664 PUN-6X1-BL PLASTIC TUBING 20 m 20.000 FESTO 36.49 729.80 4100003203 29-08-2026 FESTO 50 0 20 PENDING
Standard No 159666 PUN-8X1.25-BL PLASTIC TUBING 20m 20.000 FESTO 52.43 1,048.60 4100003203 29-08-2026 FESTO 0 0 20 NOT ORDERED
Standard No 7849 FR-4-1/4-C Distribution Block 1.000 FESTO 263.70 263.70 4100003203 29-08-2026 FESTO 1 0 1 PENDING
Standard No 3569 B-1/4 Blanking Plug 5.000 FESTO 58.27 291.35 4100003203 29-08-2026 FESTO 10 0 5 PENDING
Standard No UWAUNS120 HANDLE 10.000 Misumi 301.00 3,010.00 4100003277 08-09-2026 SAI RAM 10 0 10 PENDING
Standard No 45X45 AL PROFILE 35 m 35.000 ALSTRUT 0.00 0.00 0 0 35 NOT ORDERED
Standard No 30X30 AL PROFILE 5 m 5.000 ALSTRUT 0.00 0.00 0 0 5 NOT ORDERED
Standard No 45X45 L-CONNECTOR 60.000 STD 0.00 0.00 0 0 60 NOT ORDERED
Standard No 30X30 L-CONNECTOR 10.000 STD 0.00 0.00 0 0 10 NOT ORDERED
Standard No DHUDH-120 HANDLE 2.000 DHARSANA 0.00 0.00 0 0 2 NOT ORDERED
Standard No SHHPS8-2 DOOR HINGES 4.000 STD 0.00 0.00 0 0 4 NOT ORDERED
Standard No HGH25CA1R920Z0H (E1=E2=40) LM RAIL & BLOCK 2.000 HIWIN 6,100.00 12,200.00 4100003278 08-09-2026 International 2 0 2 PENDING
SPM817-11 REJECTION BIN Standard No 30-100 DOOR HINGE 3.000 STD 0.00 0.00 0 0 3 NOT ORDERED
Standard No DHUDH-120 HANDLE 1.000 DHARSANA 0.00 0.00 0 0 1 NOT ORDERED
Electrical No GRC SPINNING MACHINE PANEL 1.000 365,596.00 365,596.00 4100003251 04-09-2026 GAGNER 1 0 1 PENDING
Electrical No GL-VB21 MOUNTING BRACKET 2.000 1,100.00 2,200.00 4100003200 28-08-2026 KEYENCE INDIA 2 0 2 PENDING
Electrical No GL-VP5S Safety Light Curtain 1.000 2,800.00 2,800.00 4100003200 28-08-2026 KEYENCE INDIA 1 0 1 PENDING
Electrical No GL-VM119FP Safety Light Curtain 1.000 46,000.00 46,000.00 4100003200 28-08-2026 KEYENCE INDIA 1 0 1 PENDING
Electrical No GS-M51P SAFETY INTERLOCK - POWER TO LOCK 1.000 5,500.00 5,500.00 4100003200 28-08-2026 KEYENCE INDIA 1 0 1 PENDING
Electrical No GS-MA5M SAFETY INTERLOCK ACTUATOR 1.000 2,200.00 2,200.00 4100003200 28-08-2026 KEYENCE INDIA 1 0 1 PENDING
Electrical No GS-P8C5 CABLE 2.000 2,200.00 4,400.00 4100003200 28-08-2026 KEYENCE INDIA 2 0 2 PENDING
Electrical No GS-51PC DOOR SWITCH 1.000 8,900.00 8,900.00 4100003200 28-08-2026 KEYENCE INDIA 1 0 1 PENDING
Electrical No IME18-08BPSZC0S Proximity sensor 2.000 741.00 1,482.00 4100003195 27-08-2026 SICK INDIA PVT LTD 2 0 2 PENDING
Electrical No GTB6-P4231 Diffuse Sensor 2.000 2,114.00 4,228.00 4100003195 27-08-2026 SICK INDIA PVT LTD 2 0 2 PENDING
Electrical No IME12-04BPSZC0K Proximity sensor 3.000 608.00 1,824.00 4100003195 27-08-2026 SICK INDIA PVT LTD 3 0 3 PENDING
Electrical No MZT7-03VPS-KP0 Reed Swich 6.000 660.00 3,960.00 4100003195 27-08-2026 SICK INDIA PVT LTD 6 0 6 PENDING
Electrical No GSE6-P4212 Thru Beam 2.000 1,717.00 3,434.00 4100003195 27-08-2026 SICK INDIA PVT LTD 2 0 2 PENDING
Electrical No YG2A14-050UB3XLEAX M12 Sensor Cable 5.000 432.00 2,160.00 4100003195 27-08-2026 SICK INDIA PVT LTD 5 0 5 PENDING
Electrical No YG8U14-050UA3XLEAX M8 4 Pin Angle Cable 5.000 810.00 4,050.00 4100003195 27-08-2026 SICK INDIA PVT LTD 5 0 5 PENDING
Electrical No YF8U14-050UA3XLEAX M8 4Pin Straight Cabl 1.000 750.00 750.00 4100003195 27-08-2026 SICK INDIA PVT LTD 1 0 1 PENDING
Electrical No YF8U13-050UA1XLEAX M8 3 Pin Straight Ca 6.000 935.00 5,610.00 4100003195 27-08-2026 SICK INDIA PVT LTD 6 0 6 PENDING
Electrical No 2000 Kg Load Cell Button type. 2.000 21,000.00 42,000.00 4100003198 27-08-2026 SYSCON 2 0 2 PENDING
Electrical No Signal Conditioner (without display) 2.000 15,500.00 31,000.00 4100003198 27-08-2026 SYSCON 2 0 2 PENDING
Electrical No V3L Face + Finger Card Reader 1.000 23,000.00 23,000.00 4100003199 27-08-2026 Axis Automation 1 0 1 PENDING
Electrical No R08ENCPU, iQ-R PLC Series; 1.000 100,695.75 100,695.75 4100003111 14-08-2026 ICON AUTOMATION 1 0 1 PENDING
Electrical No RJ71EIP91, iQ-R PLC Series EtherNet/IP 1.000 116,296.50 116,296.50 4100003111 14-08-2026 ICON AUTOMATION 1 0 1 PENDING
Electrical No RX41C4-TS, iQ-R PLC Series 1.000 14,298.75 14,298.75 4100003111 14-08-2026 ICON AUTOMATION 1 0 1 PENDING
Electrical No R64P, iQ-R PLC Series Power supply, 1.000 17,856.00 17,856.00 4100003111 14-08-2026 ICON AUTOMATION 1 0 1 PENDING
Electrical No RX40C7, iQ-R PLC Series; 1.000 6,951.75 6,951.75 4100003111 14-08-2026 ICON AUTOMATION 1 0 1 PENDING
Electrical No GT2507-WTBD, Graphic Touch Terminal; 1.000 56,366.50 56,366.50 4100003111 14-08-2026 ICON AUTOMATION 1 0 1 PENDING
Electrical No R38B- BASE RACK 1.000 9,914.00 9,914.00 4100003111 14-08-2026 ICON AUTOMATION 1 0 1 PENDING
Electrical No RY41PT1P-TS, iQ-R PLC; 1.000 25,737.75 25,737.75 4100003111 14-08-2026 ICON AUTOMATION 1 0 1 PENDING
Electrical No MR-J5-12KG4-HS, 12 KW CC-LINK IE 1.000 244,800.00 244,800.00 4100003047 07-08-2026 ICON AUTOMATION 1 0 1 PENDING
Electrical No HK-JT11K1M4J, 11 KW 1500 rpm 1.000 280,000.00 280,000.00 4100003047 07-08-2026 ICON AUTOMATION 1 0 1 PENDING
Electrical No MR-J3ENSCBL5M-H, 5m Encoder Cable 1.000 4,780.00 4,780.00 4100003047 07-08-2026 ICON AUTOMATION 1 0 1 PENDING
Electrical No MR-APWCNS3, Motor power connector 1.000 11,840.00 11,840.00 4100003047 07-08-2026 ICON AUTOMATION 1 0 1 PENDING
Electrical No DBU-11K-4, Dynamic brake (200 V AC) 1.000 23,740.00 23,740.00 4100003047 07-08-2026 ICON AUTOMATION 1 0 1 PENDING
Electrical No RD78G4, CC-Link IE TSN 4 axes 1.000 64,719.00 64,719.00 4100003047 07-08-2026 ICON AUTOMATION 1 0 1 PENDING
Previous uploads
  • 22-09-2026 11:58 · Standard_BOM_Template (002) (1).xlsx (318 lines, 3,160,100.02) by contact@themars.in · Download
  • 22-09-2026 11:55 · Standard_BOM_Template (002).xlsx (318 lines, 3,160,100.02) by contact@themars.in · Download
  • 18-09-2026 16:26 · Standard_BOM_Template (002) - Copy.xlsx (318 lines, 3,160,100.02) by contact@themars.in · Download
  • 18-09-2026 09:25 · Standard_BOM_Template (002).xlsx (318 lines, 3,160,100.02) by contact@themars.in · Download
Timeline & Gantt Chart (Plan vs Actual)

A curated set of milestones, each covering a range of Process Flow Checklist tasks - each one shown as a weekly Plan row and Actual row, filled in for every calendar week its dates span. Nothing here is editable directly; update the checklist instead, or the milestone list itself under Master Data → Gantt Milestones.

Milestone Wk29 Wk30 Wk31 Wk32 Wk33 Wk34 Wk35 Wk36 Wk37 Wk38 Wk39 Wk40 Wk41 Wk42 Wk43 Wk44 Wk45 Wk46 Status
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
2026 2026 2026 2026 2026 2026 2026 2026 2026 2026 2026 2026 2026 2026 2026 2026 2026 2026
Design review for Mfg/assembly Delayed
Design review for routing & accessibility Delayed
STD BOM release Delayed
Electrical BOM release Delayed
STD RFQ, order finalization & PO release On track
Electrical order release On track
Manufacturing BOM release On track
Mfg RFQ, order finalization & PO release On track
Manufacturing & Procurement On track
Electrical items Procurement On track
Standard items Procurement On track
Assembly & Alignment completion On track
Electrical wiring & routing completion On track
Internal Testing On track
Trial-1 at GTRP On track
Despatch On track